Cost and Management Accounting: Marginal Costing, Standard Costing, Budgets, ABC

UGC NET Commerce: break-even analysis, variances, budgetary control, process costing, ABC, decision-making, life cycle, target and kaizen costing, JIT.

  • 18 min read
  • Updated
On this page · 16 sections
  1. Prerequisites
  2. The Hook: The Order That Looks Like a Loss
  3. 1. Marginal Costing and Break-even (CVP) Analysis
  4. 2. Costing for Decision-making
  5. 3. Standard Costing and Variance Analysis
  6. 4. Budgetary Control
  7. 5. Process Costing
  8. 6. Activity Based Costing (ABC)
  9. 7. Modern Cost Management: Life Cycle, Target, Kaizen and JIT
  10. Memory Tricks
  11. Don’t Confuse
  12. Common Mistakes
  13. Practice
  14. Quick Revision Table
  15. Key Takeaways
  16. What’s Next

Prerequisites

This page covers the official line “Cost and management accounting: marginal costing and break-even analysis; standard costing; budgetary control; process costing; Activity Based Costing (ABC); costing for decision-making; life cycle costing, target costing, kaizen costing and JIT”. It is the most numerical part of the unit.

The Hook: The Order That Looks Like a Loss


1. Marginal Costing and Break-even (CVP) Analysis

Absorption vs marginal costing

PointAbsorption costingMarginal costing
Fixed production overheadPart of product cost; in inventoryPeriod cost; written off in full
Stock valuationHigher (includes fixed overhead)Lower (variable cost only)
Profit when production > salesHigher than marginalLower
Profit when production < salesLowerHigher
Key measureGross profitContribution

The formulas

$$\text{Contribution} = \text{Sales} - \text{Variable cost} = \text{Fixed cost} + \text{Profit}$$
MeasureFormula
P/V ratio\( \dfrac{\text{Contribution}}{\text{Sales}} \times 100 \), or \( \dfrac{\Delta \text{Profit}}{\Delta \text{Sales}} \times 100 \)
BEP (units)\( \dfrac{\text{Fixed cost}}{\text{Contribution per unit}} \)
BEP (sales value)\( \dfrac{\text{Fixed cost}}{\text{P/V ratio}} \)
Sales for target profit\( \dfrac{\text{Fixed cost} + \text{Target profit}}{\text{P/V ratio}} \)
Margin of safety (MOS)Actual sales − BEP sales = \( \dfrac{\text{Profit}}{\text{P/V ratio}} \)
ProfitMOS × P/V ratio
Angle of incidenceAngle at which the sales line cuts the total cost line; a large angle means a high rate of profit

Assumptions of CVP analysis: costs can be split into fixed and variable; fixed cost is constant and variable cost per unit is constant over the relevant range; selling price is constant; sales mix is constant; production equals sales (no change in stock).


2. Costing for Decision-making

The rule: only relevant costs matter, i.e. future costs that differ between alternatives. Sunk costs (already incurred) and committed fixed costs that do not change are irrelevant. Opportunity cost is relevant.

DecisionRule
Special order / export order below normal priceAccept if price > marginal cost (and capacity is spare, no effect on regular market)
Make or buyBuy if purchase price < avoidable cost of making (variable + avoidable fixed)
Shut down or continueContinue while contribution > avoidable fixed costs (in the short run, while price ≥ variable cost)
Product mix with a key (limiting) factorRank by contribution per unit of the key factor
Drop a productDrop only if its contribution is lower than the fixed costs saved by dropping it

3. Standard Costing and Variance Analysis

A standard cost is a pre-determined cost of what a unit should cost under efficient conditions. Variance = standard − actual. A variance is favourable (F) when actual cost is below standard, adverse (A) when it is above.

Material variances

Let SQ = standard quantity for actual output, AQ = actual quantity, SP = standard price, AP = actual price.

VarianceFormula
Material cost variance (MCV)\( (SQ \times SP) - (AQ \times AP) \)
Material price variance (MPV)\( AQ \times (SP - AP) \)
Material usage variance (MUV)\( SP \times (SQ - AQ) \)
Material mix variance\( SP \times (RSQ - AQ) \), RSQ = revised standard quantity (actual total in standard proportions)
Material yield variance\( SP \times (SQ - RSQ) \)

Check: MCV = MPV + MUV, and MUV = mix + yield.

Labour variances

Let SH = standard hours for actual output, AH = actual hours paid, SR = standard rate, AR = actual rate.

VarianceFormula
Labour cost variance (LCV)\( (SH \times SR) - (AH \times AR) \)
Labour rate variance (LRV)\( AH \times (SR - AR) \)
Idle time varianceIdle hours × SR (always adverse)
Labour efficiency variance (LEV)\( SR \times (SH - \text{actual hours worked}) \)

Check: LCV = LRV + idle time variance + LEV.

Overhead and sales variances (outline)

  • Variable overhead: expenditure (spending) variance and efficiency variance.
  • Fixed overhead: expenditure (budget) variance and volume variance; volume splits into capacity, efficiency and calendar variances.
  • Sales: sales price variance and sales volume variance (computed on value or on margin/contribution).

4. Budgetary Control

A budget is a quantitative plan for a future period; budgetary control compares actual results with the budget, finds variances, and acts on them. A budget manual sets procedures; a budget committee coordinates; the budget period is usually a year, split into months.

Principal (key, limiting) budget factor: the factor that limits activity (often sales; sometimes materials, labour or plant capacity). It is identified first, and the budget built around it.

TypeMeaning
Fixed budgetPrepared for one level of activity; not adjusted
Flexible budgetPrepared for several levels; costs split into fixed, variable and semi-variable; actual compared with the budget for the actual level
Functional budgetsSales, production, materials, labour, overhead, cash
Master budgetSummary of all functional budgets: budgeted P&L and balance sheet
Cash budgetForecast of receipts and payments; shows surplus or deficit
Zero-based budgeting (ZBB)Every activity justified afresh from zero each period (associated with Peter Pyhrr at Texas Instruments)
Performance budgetingBudget linked to programmes, activities and measurable outputs (used in government)
Rolling (continuous) budgetA new period added as the earliest ends

5. Process Costing

Used where production passes through continuous processes and units are identical (chemicals, cement, textiles, oil refining). Costs are accumulated by process, and the output of one process becomes the input of the next.

ItemTreatment
Normal lossExpected, unavoidable; its cost is absorbed by good units; scrap value credited to the process
Abnormal lossLoss above normal; valued like good units and transferred to Abnormal Loss A/c, then to Costing P&L (net of scrap)
Abnormal gainActual loss below normal; valued like good units; credited to Costing P&L after adjusting lost scrap value
Equivalent unitsIncomplete units expressed as complete ones (e.g. 200 units 50% complete = 100 equivalent units)
Joint productsTwo or more products of equal importance from the same process (petrol, diesel, kerosene); joint cost apportioned (physical units, sales value)
By-productsProducts of small value incidental to the main product (molasses from sugar); sale value usually credited to the main process

6. Activity Based Costing (ABC)

ABC was developed by Robin Cooper and Robert S. Kaplan (Harvard Business School) in the late 1980s. Traditional costing spreads overhead on one volume base (labour or machine hours), so high-volume simple products subsidise low-volume complex ones. ABC traces overheads to activities and charges them to products by cost drivers.

Steps: identify activities → form activity cost pools → choose cost drivers (number of set-ups, purchase orders, inspections, machine hours) → compute cost driver rates → charge products by their use of drivers.

Cost hierarchy (Cooper): unit-level, batch-level, product-sustaining, facility-sustaining activities.


7. Modern Cost Management: Life Cycle, Target, Kaizen and JIT

TechniqueCore ideaAssociated with
Life cycle costingTracks and accumulates all costs of a product over its whole life, from research and design to decline and disposal; most costs are committed at the design stageProduct life-cycle thinking; defence and government procurement
Target costingTarget cost = target (market) price − desired profit. Price is set by the market; cost is engineered down to fit, mainly at the design stageJapanese industry (Toyota is the usual example)
Kaizen costingContinuous, small, incremental cost reductions during the manufacturing stageKaizen (“continuous improvement”), popularised by Masaaki Imai
JIT (Just-in-Time)Produce and buy only what is needed, when it is needed; near-zero inventory; pull system; backflush costingToyota Production System (Taiichi Ohno); kanban cards

Memory Tricks

Don’t Confuse

PairFirstSecond
Marginal vs absorption costingFixed overhead a period costFixed overhead in product cost and stock
Normal vs abnormal lossAbsorbed by good unitsValued like good units, written off to Costing P&L
Joint product vs by-productEqual importanceMinor, incidental
Fixed vs flexible budgetOne activity levelAdjusts to actual activity
Target vs kaizen costingDesign stage, market-ledProduction stage, continuous improvement
ABC vs traditionalMany cost pools and driversOne volume-based rate
Sunk vs opportunity costPast, irrelevantBenefit forgone, relevant

Common Mistakes


Practice

All questions below are original practice questions written in the UGC NET format. They are not previous-year questions.

Level 1: Foundation

  1. If fixed cost is ₹90,000 and the P/V ratio is 30%, what is the BEP in sales value?
  2. Which variance is always adverse?
  3. Who developed Activity Based Costing?
Answers
  1. ₹90,000 ÷ 0.30 = ₹3,00,000.
  2. Idle time variance.
  3. Robin Cooper and Robert S. Kaplan.

Level 2: Exam-style MCQs

Q1. (Practice) Sales ₹6,00,000; P/V ratio 25%; fixed cost ₹1,00,000. The margin of safety is:

  • (a) ₹2,00,000
  • (b) ₹4,00,000
  • (c) ₹50,000
  • (d) ₹1,50,000
Answer and explanation

(a) ₹2,00,000. BEP = ₹1,00,000 ÷ 0.25 = ₹4,00,000; MOS = ₹6,00,000 − ₹4,00,000 = ₹2,00,000. (Check: profit = ₹2,00,000 × 25% = ₹50,000 = ₹1,50,000 contribution − ₹1,00,000.)

Q2. (Practice) Standard mix for 100 kg of output: material A 60 kg at ₹5 and material B 40 kg at ₹10. Actual input: A 70 kg, B 30 kg. The material mix variance is:

  • (a) ₹50 A
  • (b) ₹50 F
  • (c) ₹100 F
  • (d) Nil
Answer and explanation

(b) ₹50 F. Actual total = 100 kg, so RSQ = 60 kg A and 40 kg B. Mix variance = 5(60 − 70) + 10(40 − 30) = −50 + 100 = ₹50 F. More of the cheaper material was used.

Q3. (Practice) In the short run, a firm should continue production as long as:

  • (a) Price covers total cost
  • (b) Price covers variable cost
  • (c) Price covers fixed cost
  • (d) Profit is positive
Answer and explanation

(b). As long as there is some contribution, it reduces the loss from fixed costs that are incurred anyway.

Q4. (Practice) Consider the following statements:

  1. Under marginal costing, closing stock is valued at variable cost.
  2. When production exceeds sales, absorption costing shows a higher profit than marginal costing.
  3. Marginal costing treats fixed production overhead as a product cost.

Which of the statements given above is/are correct?

  • (a) 1 and 2 only
  • (b) 2 and 3 only
  • (c) 1 and 3 only
  • (d) 1, 2 and 3
Answer and explanation

(a) 1 and 2 only. Statement 3 describes absorption costing. Statement 2 holds because part of the fixed overhead is carried forward in stock under absorption costing.

Level 3: Assertion–reason, match and sequence

For assertion–reason questions, use these options:

  • (a) Both A and R are true, and R is the correct explanation of A
  • (b) Both A and R are true, but R is not the correct explanation of A
  • (c) A is true, but R is false
  • (d) A is false, but R is true

Q1. (Practice) Assertion (A): Traditional absorption costing tends to under-cost low-volume, complex products. Reason (R): Traditional costing allocates overheads on volume-based bases such as labour or machine hours.

Answer and explanation

(a). Batch and product-level costs such as set-ups do not vary with volume, so a volume base shifts them to high-volume products.

Q2. (Practice) Assertion (A): Target costing is mainly applied at the manufacturing stage of a product’s life. Reason (R): In target costing, the selling price is determined by the market and the cost must be fitted to it.

Answer and explanation

(d). A is false: target costing works mainly at the design stage, where most costs are committed. R is true. (Kaizen costing is the manufacturing-stage technique.)

Q3. (Practice) Match List I with List II.

List I (Technique)List II (Feature)
A. JITI. Continuous small improvements during production
B. Kaizen costingII. Cost drivers and activity cost pools
C. ABCIII. Pull system with minimal inventory
D. Life cycle costingIV. Costs from design to disposal
  • (1) A-III, B-I, C-II, D-IV
  • (2) A-I, B-III, C-II, D-IV
  • (3) A-III, B-II, C-I, D-IV
  • (4) A-IV, B-I, C-II, D-III
Answer and explanation

(1) A-III, B-I, C-II, D-IV.

Q4. (Practice) Arrange the steps of activity based costing in order:

  • A. Calculate cost driver rates

  • B. Identify activities

  • C. Charge costs to products according to their use of drivers

  • D. Create activity cost pools

  • E. Select cost drivers

  • (1) B, D, E, A, C

  • (2) D, B, E, A, C

  • (3) B, E, D, A, C

  • (4) B, D, A, E, C

Answer and explanation

(1) B, D, E, A, C.


Quick Revision Table

ItemFormula / fact
ContributionSales − VC = FC + Profit
P/V ratioContribution ÷ Sales; or ΔProfit ÷ ΔSales
BEPFC ÷ contribution per unit (units); FC ÷ P/V (value)
MOSActual sales − BEP sales = Profit ÷ P/V
MCV = MPV + MUV(SQ×SP − AQ×AP) = AQ(SP − AP) + SP(SQ − AQ)
LCV = LRV + idle + LEVAH(SR − AR); idle hrs × SR; SR(SH − hours worked)
Key factorRank by contribution per unit of the limiting factor
Flexible budgetSplit semi-variable costs; budget for actual activity
ZBBEvery activity justified from zero; Peter Pyhrr
Normal / abnormal lossAbsorbed / valued like good units
ABCCooper and Kaplan; activities, pools, drivers
Target costMarket price − desired profit; design stage
KaizenContinuous improvement; production stage; Masaaki Imai
JITToyota Production System; pull; kanban; backflush costing

Key Takeaways

What’s Next