- The Hook: The Order That Looks Like a Loss
- 1. Marginal Costing and Break-even (CVP) Analysis
- 2. Costing for Decision-making
- 3. Standard Costing and Variance Analysis
- 4. Budgetary Control
- 5. Process Costing
- 6. Activity Based Costing (ABC)
- 7. Modern Cost Management: Life Cycle, Target, Kaizen and JIT
- Memory Tricks
- Don’t Confuse
- Common Mistakes
- Practice
- Quick Revision Table
- Key Takeaways
- What’s Next
Prerequisites
- Accounting Principles, Concepts and Standards — matching and conservatism carry over to inventory valuation in costing.
- Accounting and Auditing: chapter overview.
- Comfort with simple algebra and percentages. Paper 1: Research Aptitude is useful for the idea of controlled comparison behind variance analysis.
This page covers the official line “Cost and management accounting: marginal costing and break-even analysis; standard costing; budgetary control; process costing; Activity Based Costing (ABC); costing for decision-making; life cycle costing, target costing, kaizen costing and JIT”. It is the most numerical part of the unit.
The Hook: The Order That Looks Like a Loss
1. Marginal Costing and Break-even (CVP) Analysis
Absorption vs marginal costing
| Point | Absorption costing | Marginal costing |
|---|---|---|
| Fixed production overhead | Part of product cost; in inventory | Period cost; written off in full |
| Stock valuation | Higher (includes fixed overhead) | Lower (variable cost only) |
| Profit when production > sales | Higher than marginal | Lower |
| Profit when production < sales | Lower | Higher |
| Key measure | Gross profit | Contribution |
The formulas
$$\text{Contribution} = \text{Sales} - \text{Variable cost} = \text{Fixed cost} + \text{Profit}$$| Measure | Formula |
|---|---|
| P/V ratio | \( \dfrac{\text{Contribution}}{\text{Sales}} \times 100 \), or \( \dfrac{\Delta \text{Profit}}{\Delta \text{Sales}} \times 100 \) |
| BEP (units) | \( \dfrac{\text{Fixed cost}}{\text{Contribution per unit}} \) |
| BEP (sales value) | \( \dfrac{\text{Fixed cost}}{\text{P/V ratio}} \) |
| Sales for target profit | \( \dfrac{\text{Fixed cost} + \text{Target profit}}{\text{P/V ratio}} \) |
| Margin of safety (MOS) | Actual sales − BEP sales = \( \dfrac{\text{Profit}}{\text{P/V ratio}} \) |
| Profit | MOS × P/V ratio |
| Angle of incidence | Angle at which the sales line cuts the total cost line; a large angle means a high rate of profit |
Assumptions of CVP analysis: costs can be split into fixed and variable; fixed cost is constant and variable cost per unit is constant over the relevant range; selling price is constant; sales mix is constant; production equals sales (no change in stock).
2. Costing for Decision-making
The rule: only relevant costs matter, i.e. future costs that differ between alternatives. Sunk costs (already incurred) and committed fixed costs that do not change are irrelevant. Opportunity cost is relevant.
| Decision | Rule |
|---|---|
| Special order / export order below normal price | Accept if price > marginal cost (and capacity is spare, no effect on regular market) |
| Make or buy | Buy if purchase price < avoidable cost of making (variable + avoidable fixed) |
| Shut down or continue | Continue while contribution > avoidable fixed costs (in the short run, while price ≥ variable cost) |
| Product mix with a key (limiting) factor | Rank by contribution per unit of the key factor |
| Drop a product | Drop only if its contribution is lower than the fixed costs saved by dropping it |
3. Standard Costing and Variance Analysis
A standard cost is a pre-determined cost of what a unit should cost under efficient conditions. Variance = standard − actual. A variance is favourable (F) when actual cost is below standard, adverse (A) when it is above.
Material variances
Let SQ = standard quantity for actual output, AQ = actual quantity, SP = standard price, AP = actual price.
| Variance | Formula |
|---|---|
| Material cost variance (MCV) | \( (SQ \times SP) - (AQ \times AP) \) |
| Material price variance (MPV) | \( AQ \times (SP - AP) \) |
| Material usage variance (MUV) | \( SP \times (SQ - AQ) \) |
| Material mix variance | \( SP \times (RSQ - AQ) \), RSQ = revised standard quantity (actual total in standard proportions) |
| Material yield variance | \( SP \times (SQ - RSQ) \) |
Check: MCV = MPV + MUV, and MUV = mix + yield.
Labour variances
Let SH = standard hours for actual output, AH = actual hours paid, SR = standard rate, AR = actual rate.
| Variance | Formula |
|---|---|
| Labour cost variance (LCV) | \( (SH \times SR) - (AH \times AR) \) |
| Labour rate variance (LRV) | \( AH \times (SR - AR) \) |
| Idle time variance | Idle hours × SR (always adverse) |
| Labour efficiency variance (LEV) | \( SR \times (SH - \text{actual hours worked}) \) |
Check: LCV = LRV + idle time variance + LEV.
Overhead and sales variances (outline)
- Variable overhead: expenditure (spending) variance and efficiency variance.
- Fixed overhead: expenditure (budget) variance and volume variance; volume splits into capacity, efficiency and calendar variances.
- Sales: sales price variance and sales volume variance (computed on value or on margin/contribution).
4. Budgetary Control
A budget is a quantitative plan for a future period; budgetary control compares actual results with the budget, finds variances, and acts on them. A budget manual sets procedures; a budget committee coordinates; the budget period is usually a year, split into months.
Principal (key, limiting) budget factor: the factor that limits activity (often sales; sometimes materials, labour or plant capacity). It is identified first, and the budget built around it.
| Type | Meaning |
|---|---|
| Fixed budget | Prepared for one level of activity; not adjusted |
| Flexible budget | Prepared for several levels; costs split into fixed, variable and semi-variable; actual compared with the budget for the actual level |
| Functional budgets | Sales, production, materials, labour, overhead, cash |
| Master budget | Summary of all functional budgets: budgeted P&L and balance sheet |
| Cash budget | Forecast of receipts and payments; shows surplus or deficit |
| Zero-based budgeting (ZBB) | Every activity justified afresh from zero each period (associated with Peter Pyhrr at Texas Instruments) |
| Performance budgeting | Budget linked to programmes, activities and measurable outputs (used in government) |
| Rolling (continuous) budget | A new period added as the earliest ends |
5. Process Costing
Used where production passes through continuous processes and units are identical (chemicals, cement, textiles, oil refining). Costs are accumulated by process, and the output of one process becomes the input of the next.
| Item | Treatment |
|---|---|
| Normal loss | Expected, unavoidable; its cost is absorbed by good units; scrap value credited to the process |
| Abnormal loss | Loss above normal; valued like good units and transferred to Abnormal Loss A/c, then to Costing P&L (net of scrap) |
| Abnormal gain | Actual loss below normal; valued like good units; credited to Costing P&L after adjusting lost scrap value |
| Equivalent units | Incomplete units expressed as complete ones (e.g. 200 units 50% complete = 100 equivalent units) |
| Joint products | Two or more products of equal importance from the same process (petrol, diesel, kerosene); joint cost apportioned (physical units, sales value) |
| By-products | Products of small value incidental to the main product (molasses from sugar); sale value usually credited to the main process |
6. Activity Based Costing (ABC)
ABC was developed by Robin Cooper and Robert S. Kaplan (Harvard Business School) in the late 1980s. Traditional costing spreads overhead on one volume base (labour or machine hours), so high-volume simple products subsidise low-volume complex ones. ABC traces overheads to activities and charges them to products by cost drivers.
Steps: identify activities → form activity cost pools → choose cost drivers (number of set-ups, purchase orders, inspections, machine hours) → compute cost driver rates → charge products by their use of drivers.
Cost hierarchy (Cooper): unit-level, batch-level, product-sustaining, facility-sustaining activities.
7. Modern Cost Management: Life Cycle, Target, Kaizen and JIT
| Technique | Core idea | Associated with |
|---|---|---|
| Life cycle costing | Tracks and accumulates all costs of a product over its whole life, from research and design to decline and disposal; most costs are committed at the design stage | Product life-cycle thinking; defence and government procurement |
| Target costing | Target cost = target (market) price − desired profit. Price is set by the market; cost is engineered down to fit, mainly at the design stage | Japanese industry (Toyota is the usual example) |
| Kaizen costing | Continuous, small, incremental cost reductions during the manufacturing stage | Kaizen (“continuous improvement”), popularised by Masaaki Imai |
| JIT (Just-in-Time) | Produce and buy only what is needed, when it is needed; near-zero inventory; pull system; backflush costing | Toyota Production System (Taiichi Ohno); kanban cards |
Memory Tricks
Don’t Confuse
| Pair | First | Second |
|---|---|---|
| Marginal vs absorption costing | Fixed overhead a period cost | Fixed overhead in product cost and stock |
| Normal vs abnormal loss | Absorbed by good units | Valued like good units, written off to Costing P&L |
| Joint product vs by-product | Equal importance | Minor, incidental |
| Fixed vs flexible budget | One activity level | Adjusts to actual activity |
| Target vs kaizen costing | Design stage, market-led | Production stage, continuous improvement |
| ABC vs traditional | Many cost pools and drivers | One volume-based rate |
| Sunk vs opportunity cost | Past, irrelevant | Benefit forgone, relevant |
Common Mistakes
Practice
All questions below are original practice questions written in the UGC NET format. They are not previous-year questions.
Level 1: Foundation
- If fixed cost is ₹90,000 and the P/V ratio is 30%, what is the BEP in sales value?
- Which variance is always adverse?
- Who developed Activity Based Costing?
Answers
- ₹90,000 ÷ 0.30 = ₹3,00,000.
- Idle time variance.
- Robin Cooper and Robert S. Kaplan.
Level 2: Exam-style MCQs
Q1. (Practice) Sales ₹6,00,000; P/V ratio 25%; fixed cost ₹1,00,000. The margin of safety is:
- (a) ₹2,00,000
- (b) ₹4,00,000
- (c) ₹50,000
- (d) ₹1,50,000
Answer and explanation
(a) ₹2,00,000. BEP = ₹1,00,000 ÷ 0.25 = ₹4,00,000; MOS = ₹6,00,000 − ₹4,00,000 = ₹2,00,000. (Check: profit = ₹2,00,000 × 25% = ₹50,000 = ₹1,50,000 contribution − ₹1,00,000.)
Q2. (Practice) Standard mix for 100 kg of output: material A 60 kg at ₹5 and material B 40 kg at ₹10. Actual input: A 70 kg, B 30 kg. The material mix variance is:
- (a) ₹50 A
- (b) ₹50 F
- (c) ₹100 F
- (d) Nil
Answer and explanation
(b) ₹50 F. Actual total = 100 kg, so RSQ = 60 kg A and 40 kg B. Mix variance = 5(60 − 70) + 10(40 − 30) = −50 + 100 = ₹50 F. More of the cheaper material was used.
Q3. (Practice) In the short run, a firm should continue production as long as:
- (a) Price covers total cost
- (b) Price covers variable cost
- (c) Price covers fixed cost
- (d) Profit is positive
Answer and explanation
(b). As long as there is some contribution, it reduces the loss from fixed costs that are incurred anyway.
Q4. (Practice) Consider the following statements:
- Under marginal costing, closing stock is valued at variable cost.
- When production exceeds sales, absorption costing shows a higher profit than marginal costing.
- Marginal costing treats fixed production overhead as a product cost.
Which of the statements given above is/are correct?
- (a) 1 and 2 only
- (b) 2 and 3 only
- (c) 1 and 3 only
- (d) 1, 2 and 3
Answer and explanation
(a) 1 and 2 only. Statement 3 describes absorption costing. Statement 2 holds because part of the fixed overhead is carried forward in stock under absorption costing.
Level 3: Assertion–reason, match and sequence
For assertion–reason questions, use these options:
- (a) Both A and R are true, and R is the correct explanation of A
- (b) Both A and R are true, but R is not the correct explanation of A
- (c) A is true, but R is false
- (d) A is false, but R is true
Q1. (Practice) Assertion (A): Traditional absorption costing tends to under-cost low-volume, complex products. Reason (R): Traditional costing allocates overheads on volume-based bases such as labour or machine hours.
Answer and explanation
(a). Batch and product-level costs such as set-ups do not vary with volume, so a volume base shifts them to high-volume products.
Q2. (Practice) Assertion (A): Target costing is mainly applied at the manufacturing stage of a product’s life. Reason (R): In target costing, the selling price is determined by the market and the cost must be fitted to it.
Answer and explanation
(d). A is false: target costing works mainly at the design stage, where most costs are committed. R is true. (Kaizen costing is the manufacturing-stage technique.)
Q3. (Practice) Match List I with List II.
| List I (Technique) | List II (Feature) |
|---|---|
| A. JIT | I. Continuous small improvements during production |
| B. Kaizen costing | II. Cost drivers and activity cost pools |
| C. ABC | III. Pull system with minimal inventory |
| D. Life cycle costing | IV. Costs from design to disposal |
- (1) A-III, B-I, C-II, D-IV
- (2) A-I, B-III, C-II, D-IV
- (3) A-III, B-II, C-I, D-IV
- (4) A-IV, B-I, C-II, D-III
Answer and explanation
(1) A-III, B-I, C-II, D-IV.
Q4. (Practice) Arrange the steps of activity based costing in order:
A. Calculate cost driver rates
B. Identify activities
C. Charge costs to products according to their use of drivers
D. Create activity cost pools
E. Select cost drivers
(1) B, D, E, A, C
(2) D, B, E, A, C
(3) B, E, D, A, C
(4) B, D, A, E, C
Answer and explanation
(1) B, D, E, A, C.
Quick Revision Table
| Item | Formula / fact |
|---|---|
| Contribution | Sales − VC = FC + Profit |
| P/V ratio | Contribution ÷ Sales; or ΔProfit ÷ ΔSales |
| BEP | FC ÷ contribution per unit (units); FC ÷ P/V (value) |
| MOS | Actual sales − BEP sales = Profit ÷ P/V |
| MCV = MPV + MUV | (SQ×SP − AQ×AP) = AQ(SP − AP) + SP(SQ − AQ) |
| LCV = LRV + idle + LEV | AH(SR − AR); idle hrs × SR; SR(SH − hours worked) |
| Key factor | Rank by contribution per unit of the limiting factor |
| Flexible budget | Split semi-variable costs; budget for actual activity |
| ZBB | Every activity justified from zero; Peter Pyhrr |
| Normal / abnormal loss | Absorbed / valued like good units |
| ABC | Cooper and Kaplan; activities, pools, drivers |
| Target cost | Market price − desired profit; design stage |
| Kaizen | Continuous improvement; production stage; Masaaki Imai |
| JIT | Toyota Production System; pull; kanban; backflush costing |
Key Takeaways
What’s Next
- Financial Statement Analysis and Contemporary Accounting — ratios turn the outputs of costing into performance measures
- Auditing — cost audit under Section 148 checks the cost records built here
- Company Accounts, Amalgamation and Holding Companies — revisit the financial accounting side
- Commerce overview — Business Finance and Business Economics use the same cost concepts
- Quick Revision